Published on 13 March 2026
Culvert works on Boorga Road at the Smeeth Road intersection are progressing well and Boorga Road is expected to be re-opened to through traffic from Monday 16 March 2026, under traffic control. The culvert works will be assessed today, Friday 13 March, for suitability for a superficial seal which will be installed over the weekend. The final road seal will be undertaken at a later date in conjunction with other sealing works.
Smeeth Road will remain closed with Local Residents Only Access from Jones Road until 30 April 2026.
Boorga/Smeeth Road intersection, facing north.
The scheduled closure of McCarthy Road on Monday 16 March 2026 will not proceed until Boorga Road at the Smeeth Road intersection is re-opened.
A reminder of the current and upcoming road closures:
Upcoming works requiring road closures:
More information will be provided prior to commencement of these works.
Please take extra care as there is heavy machinery and changed traffic conditions in these work areas and allow additional travel time.
Please contact Griffith City Council on 1300 176 077 and ask to speak to the Project Administration Support Officer if you have any enquiries or concerns regarding this project.