Yambil Street December Update

December 2019 - Yambil Street Stage Two Update

Kooyoo Street to Ulong Street – Northern Side

Works continue to progress on schedule on the northern side of Yambil St. Stormwater culverts have been installed along with other underground services. This has allowed good progress on the road construction.

Above: Subgrade construction being inspected by Council Engineers in preparation for placement of gravel layer 

 

Above: Water cart used for dust suppression

Above: Installation of stormwater culvert in front of Centrelink

 

Above: Looking West from Kooyoo Street, northside of Yambil Street. Property stormwater pipes connected to system, prior to placement of gravel layers

The first layer of road building gravel is being installed in preparation for kerb and guttering to be constructed early in the New Year.

Courtesy visits by Council’s Project Administration Support Officer to businesses along the works area have continued and provide a valuable opportunity to relay information and listen to any concerns.

Detours around the worksite remain in place with pedestrian access provided. The 2 hour parking limit also remains in place as requested by businesses following a survey regarding parking concerns.

Contractors have now ceased work over the holiday period and will recommence work on Monday 6 January 2020.